Premium plan is also called incentive wage system and bonus plan system.
Time and piece wages system have their own advantage and disadvantage.
By the disadvantage of them, this incentive wage system has been developed.
It is developed to provide financial benefits to skilled workers and workers are separated as skilled and unskilled.
Some common features of this system are:
· Time wages are guaranteed
· As production increase, labour remuneration also increases; but not in proportion of output.
· As efficiency increase, wage cost per unit reduces.
Under this plan, various plans have been developed.
Among them, the popular plans or systems are as follow:
Halsey Premium Plan
Rowan Plan
Taylor Plan
Gantt Task Plan
Priestman’s Plan
Scanlon’s Plan
Click on the photo for FREE eBooks
This is the combination of Halsey and Rowan premium system.
Under this system, minimum wages is guaranteed.
It protects average workers by providing time rate wages.
Efficient worker gets 20% bonus for standard work.
This system is also known progressive rate system.
There are three alternatives:
Output below standard |
Standard production x Piece rate |
Output equal standard |
Production units x Time rate @ 120% |
Output above standard |
Production units x Piece rate@120% [or given in the question] |
Keep in Mind (KIM)
If any worker produces less than standard output, he/she will receive minimum guarantee wages |
Total wage = Standard production x Piece rate |
The main advantages of Gantt task system are:
· It ensures guaranteed time wage to workers who are below average workers.
· This system encourages to improve their production level.
· This system is very useful in job involve activities.
· As production increases, cost per unit decreases.
The main disadvantages of Gantt task system are:
Minimum wage is guaranteed if worker produced less than standard production.
It is not good for the worker who produces standard output.
This system is not accepted by labour union because it brings dis-unity between workers.
###########
Click on the link for YouTube videos |
|
Accounting Equation |
|
Journal Entries in Nepali |
|
Journal Entries |
|
Journal Entry and Ledger |
|
Ledger |
|
Subsidiary Book |
|
Cashbook |
|
Trial Balance and Adjusted Trial Balance |
|
Bank Reconciliation Statement (BRS) |
|
Depreciation |
|
|
|
Click on the link for YouTube videos chapter wise |
|
Financial Accounting and Analysis (All videos) |
|
Accounting Process |
|
Accounting for Long Lived Assets |
|
Analysis of Financial Statement |
###########
Here, Amount = Rs = $ = £ = € = ₹ = Af = ৳ = Nu = Rf = රු = Br = P = Birr = Currency of your country
PROBLEM: 7A
The extracted date is given below related to Gantt task system:
Standard production per month (30 days) 2,000 units
Wage rate per unit $3
Units produced by workers:
A 1,900 units
B 2,100 units
Required: Earning under Gantt task bonus scheme
[Answer: A = $6,000; B = $7,560]
SOLUTION
Worker A = 1,900 units
It is less than standard production. Bonus is not allowed.
He will receive minimum guarantee wages.
Total earning
= 2000 units x $3
= $6,000
Worker B = 2,100 units
It is more than standard production.
He will receive 20% bonus on piece rate.
Total earning
= 2,100 units x $3 @ 120%
= 2,100 units x $3.60
= $7,560
Click on the photo for FREE eBooks
Here, Amount = Rs = $ = £ = € = ₹ = Af = ৳ = Nu = Rf = රු = Br = P = Birr = Currency of your country
PROBLEM: 7B
The extracted date is given below related to Gantt task system:
Standard production per day |
80 units |
|
Standard working time per day |
8 hours |
|
Wage rate per hour |
$28 |
|
Above standard output wage rate per unit |
Rs 3.50 |
|
Units produced by workers: |
||
Anjana |
75 units |
|
Binita |
80 units |
|
Chanda |
90 units |
|
Required: Earning per day under Gantt task bonus scheme
[Answer: Anjana = $224; Binita = $269; Chanda = $315]
Solution:
Given and working note:
Standard output per hour = 80 units ÷ 8 hours = 10 units
Standard piece rate per unit = $28 ÷ 10 units = $2.80
Anjana = 75 units |
||
It is less than standard production. Bonus is not allowed. |
||
She will receive minimum guarantee wages. |
||
Total earning |
= 80 units x $2.80 |
|
|
= $224 |
|
|
||
Binita = 80 units |
||
It is equal to standard production. |
||
She will receive 20% bonus on piece rate. |
||
Total earning |
= 80 units x $2.80 @ 120% |
|
|
= 80 units x $3.36 |
|
|
= $268.8 or $269 |
|
|
||
Chanda = 90 units |
||
It is more than standard production. |
||
She will receive Rs 3.50 per unit |
||
Total earning |
= 90 units x $3.50 |
|
|
= $315 |
|
#####
Problems and Answers of Gantt Task System |
Here, Amount = Rs = $ = £ = € = ₹ = Af = ৳ = Nu = Rf = රු = Br = P = Birr = Currency of your country
PROBLEM: 7A
The extracted date is given below related to Gantt task system:
Standard production per day 80 units
Standard working time per day 8 hours
Wage rate per hour $32
Above standard output wage rate per unit $3.80
Units produced by workers:
Workers |
A |
B |
C |
Produced units |
75 |
80 |
100 |
Required: Earning per day under Gantt task bonus scheme
[Answer: A = $240; B = $307.20; C = $380;
* Standard piece rate = $32 ÷ 10 units = $3.20]
Here, Amount = Rs = $ = £ = € = ₹ = Af = ৳ = Nu = Rf = රු = Br = P = Birr = Currency of your country
PROBLEM: 7B
The time cards of two workers working in a factory for 100 hours reported the following details:
Workers |
Output in units |
Mr. A |
1,200 |
Miss X |
900 |
The pre-fixed standard for one unit of output is 6 minutes. The prevailing wage rate per hour is $57
Required: Under Gant’s task Bonus System: (a) Wage rate per unit; (b) Wages earned by the workers Mr. A and Miss X
[Answer: WRPU = $5.70; Total wage: A = $8,208; X = $5,700]
Here, Amount = Rs = $ = £ = € = ₹ = Af = ৳ = Nu = Rf = රු = Br = P = Birr = Currency of your country
PROBLEM: 7C
The following are the particular applicable to a work progress:
Time rate guaranteed |
$50 per hour |
Standard output |
10 units per hour |
Piece rate above high task |
$6.40 |
Working hour per day |
8 hours |
Produced by the semi-skilled workers:
Workers |
Anjana |
Ranjana |
Sanjana |
Produced units |
70 |
80 |
85 |
Required: Wages of the workers under Gantt’s task bonus plan
[Answer: A = $400; R = $480; S = $544]
***** EP Online Study *****
Thank you for investing your time.
Please comment on the article.
You can help us by sharing this post on your social media platform.
Jay Google, Jay YouTube, Jay Social Media
जय गूगल. जय युट्युब, जय सोशल मीडिया
Comment box closed